Active / Active cluster installation

Posted By:      Posted Date: September 30, 2010    Points: 0   Category :Sql Server



I have installed 2 -3 times a 2 node active/passive cluster  in both version of sql server 2005 & 2008.

Per the new requirements i have to install Active/Active clusters on both 2005 and 2008.

I have a few challenges in this regard.

1. Do i need to create independent sql groups, cluster groups and msdtc group based on the no of nodes.

2. Can i use default instance names on both the nodes.

3. Can i have multiple instances per node .(If possible means  can i map all the data drives on one node to a single sql group)

3. Any considerations need to be taken care from the memory perspective ? (failover considerations)

4. In an (N+1) multi instance cluster environment is there any possibility to choose the failover between the specified nodes.


It would be great if any one can point me in the right direction by providing any docs or any links or video links for the Active/active cluster installation.






View Complete Post

More Related Resource Links

SQL Server 2008 R2 Side by Side installation in Cluster(Active/passive on Windows 2003 SP2).


Hi all,

I came again with couple question on SQL Server 2008 R2 side by side installation in Cluster(Active/passive on Windows 2003 SP2).

1.I have already have SQL Server 2000 SP4 Installation.
2.Can I start Installation(Side by Side) from Passive node ?

3.you want me give New SQL Server Netwrok name (Instance Configuration  Screen)?.

4.you want me give New Instance ID  name (Instance Configuration  Screen)?

5.Can I chose Excixting Clustore resource group or I need to Create New group which is the best ?


Thanks in advance


Windows 2008 R2/SQL 2008 SP1 CU5 active/active cluster keeps failing

I have set up many of the same clusters in the last few months, but this cluster specifically has been having lots of problems lately.  OS: Windows Server 2008 R2 latest patches SQL: SQL Server 2008 SP1 CU5 (version: 10.0.2746) Disks: VMAX SAN In the very beginning when I set up the cluster, the cluster validation kept failing when I tried to add a node.  Turned out that we had to unjoin the servers from the domain and rejoin.  Right after that the cluster validation succeeded, the second node joined the cluster, and quorum was changed to "Node and Disk Majority".  SQL was installed and set up as active/active (one sql instance on each node).  No issues then until SQL server was actually in use.  Symptoms: SQL server has heavy ETL processing plus being a subscriber of a sql replication.  The following errors first started on 4/24 when I set up sql replication (these servers are replication subscribers): EventID: 1127, Source: FailoverCluster, Task Category: Network Manager Cluster network interface 'man1fscl01a - Hartbeat to man1fscl91b' for cluster node 'man1fscl01a' on network 'ClusterHeartBeat' failed. Run the Validate a Configuration wizard to check your network configuration. If the condition persists, check for hardware or software errors related to the network adapter. Also check for failures in any other network comp

SQL 2008 Active - Acvite Cluster

I have 2 node windows 2008 cluster server, I installed sql 2008 active - active cluster this is work fine but, when i move one instance to other clusrter server, instance has failed ( SQL Server and SQL Server Agent resusorce) and i received this event log on the server what can i do ?Thank You "The description for Event ID 19019 from source MSSQL$INSTANCE2 cannot be found. Either the component that raises this event is not installed on your local computer or the installation is corrupted. You can install or repair the component on the local computer."  

Action required on SQL Server side(Active /Passive) cluster,when Upgrade iscsci Upgrde.


Hi all

Storage engineers are planning to Upgrade storage Drive and that storage using for SQL Server 2005 Active /Passive cluster.

as DBA what action I have to take.

I am planning

1.Backup all Databases.(Inluding system)

2.Takning all Databases OFFLINE(make sure no body using Databases)


3.Stopping Instance and Agent .

which is the best way.


any advise is helpful for me.


Is it possble to create Active-Active Cluster in SQL Server 2008R2


Hi All,

Another question...
I am new to SQL Clustering.

Can we create Active-Active cluster on SQL Server 2008 R2 Server, which will be having facility to loadbalancing Databases on Clustered Hardware, i.e. some Databases will be on SQL_Cluster_Host_A and Some will be on SQL_Cluster_Host_B.

Or is there any way to configure the above thing?


SQL_Cluster_Host_A will host Database 1, and SQL_Cluster_Host_B will host Database 6,7,8,9,10.
When Host A will fail all DBs will goto Host B, and vise versa.


Add a new passive node to set up Active/Active/Passive cluster



We have a SQL cluster server running with SQL 2005 Enterprise Edition SP2 on Windows 2003 Enterprise Edition.

Currently the cluster has 2 nodes with Active/Active. Now I need to add a new node as a Passive node. So after I have done it, the cluster will be a Active/Active/Passive cluster.


Because the cluster is a production server, I need to know exactly how I add a new node onto the current cluster without breaking anything. Also this is my first time to install a passive node, so it is difficult for me to understand how to install and configure it.


I have already added the physical node onto the cluster group so I can see the new node 'paused' from the Cluster Administrator.  Now I need to install the SQL but I am too nervous to run the installation p

Setting up 2 node Active-Active SQL cluster as High availability and database mirroring at database

Hi guys
Please need your inputs and suggestions. I have always worked as junior DBA and have setup the HA but never planned for it. Please need some support here.

We have one main application: Application1 ...which is the sending data to all other application for billing, reporting, processing the orders and other stuff. This application is working right now on two Server.

Server1:  SQL Server 2005 Enterprise Edition  (Total 16 Gb RAM , SQL Server ( 4-12 GB AWE Enabled) and  2Processors (4 core each) and 836 GB of HD )

Upgrading SQL2008 Cluster Active/Active Failing to upgrade 2nd node


I upgraded the 1st node of a SQL2008 Cluster on Windows 2003 sp2, and this was after correcting a SQL2008 Cluster install by uninstalling and removing a node.   It was stable when I began the R2 install.  The first node went as planned, but it will not move past the setup phase where it does the install of the setup files, and the log shows this:

Running Action: PostMsiTimingConfigAction
2010-11-04 09:52:52 Slp: The object state property 'workflow' is null/empty.
2010-11-04 09:52:52 Slp: Error: Action "PostMsiTimingConfigAction" failed during execution.
2010-11-04 09:52:52 Slp: Completed Action: PostMsiTimingConfigAction, returned False


I had previously tried to install R2 which led to some corruption and required me to correct the 2008 install.  Following the instructions here :



question about applying 2008 SP1 on a active passive cluster


In the past (SS 2005), I was able to apply patches to to the virtual cluster host and it automatically detected both nodes and applied the patch.  This incurred downtime due to a reboot, but i did not care since this was a new cluster build.

Now, in 2008, the information I am finding implies that you should apply on passive node, perform a failover and then apply on other node.  

I am curious if it is still possible to apply the patch like i did for SS 2005, where I just run the install a single time from the virtual cluster host, thereby letting the installer figure out  it is a cluster and apply to both nodes?

How to re-enable clustered node from previously Passive back to Active cluster?


Hi all experts,


I pretty new in SQL database along with WinServ clustering, so please mind my knowledge level in the overall process.


Base on the screenshot above, we have currently a single cluster created base in which that is controlling DB1 and DB2. Primarily DB1 would be our Active node whereas DB2 would be our Passive, both have it's own designated Public and Private IP. After a small issue previously in which our cluster service failed, it seems that the failover has taken place in which at the moment is running on DB2, which bears the question now is would it be possible to have DB1 being the Active node without downtime? and what is the process flow to change reactivate it back?

Servers Details:

- Win2k3 Ent Application Server

- Win2k3 Ent DB1&2

- IBM DS5020 SAN Storage

On the disk management on each DB servers, we are not able to see the LUNs in DB1 (shown as Unreadable) whereas on DB2 it is shown as normal, in which we would assume that this is normal since DB2 is the active node.

Thanks for reading & most of my search base on this question ended up in this forum, which I would assume that this is the correct place to ask.


Adding a new instance on a Active\Passive SQL2008 Cluster

I have a SQL2008 (Windows Server 2008) cluster with currently one SQL instance on it. I would like to add a second SQL 2008 instance on the cluster. I know it needs it's own IP.  What do I need to do overall? How do I install it? Is it the same where I install a new "named" instance on Node A and then do the same on Node B?  Maybe someone knows a good resource out there that takes you through this?

Thanks in advance.

Memory allocation of Active/Passive Cluster SQL2008


Can any one point me to a microsoft paper that cleary highlights the memory requirements of the passive node. I want to confirm that it needs to have the same memoery avaliable in the machine as the active node. I have been told that I doesn't.

The current active node has 16gb of ram with 4gb allocated to the os and the other split across 3 sql instances. The passive node currently only has 8gb of RAM, wouldn't it need 16gb if that is what has been allocated.

Automatically redirect to HTTPS and check if SSL is active



I've set in the web.config:

    <!-- User Authentication -->
    <authentication mode="Forms">
      <forms loginUrl="~/Page/View/Content/Login.aspx" timeout="2880" requireSSL="true" />

This works fine. If there is no ssl connection, the login form doesn't continue. But I would like to check if ssl is active (in codebehind) and, if it's possible, to automatically the user to the https page if he's currently on http. (I could do this job by manually redirect with page.response("https://url.../login.aspx"); but this is not really generic. For example if the webapp is moved to another domain it doesn't work anymore... I'm looking for something like: FormsAuthentication.RedirectWithSSL(); or so... :D)


How to set SearchRoot Path in Active Directory in this scenario


How to set SearchRoot Path in Active Directory in this scenario:

Functionality: We have scenario that 1<sup>st</sup> hit one LDAP server with some 'fixed user name' &' fixed password ' and filter data with specific User name(which given by user) getting 'User dn'.

After that we hit Next LDAP server based on the 'User dn' getting from 1<sup>st</sup> server.

(So, in my case 1<sup>st</sup> LDAP server works like as Load balancing server but functionalitywise it is different)


active directory exception unusual behaviour


i have a small problem
i want user names from active directory for an auto completer type of service
the method is always throwing an exception 
"searcher.FindAll()' threw an exception of type 'System.DirectoryServices.DirectoryServicesCOMException' System.DirectoryServices.SearchResultCollection 

Active Directory and .NET: paging the search result

Hi everybody!

I have a question about Active Directory in .NET
For my project I need to fetch results from Active Directory search page by page, because later I would need to bind it to the pageable DataGrid.

I tried to use .NET library DirectoryServices for that, but paging provided by this library is transparent to the user and is used only to increase the efficiency of searching, when results are too big. I.e. I cannot tell the DirectorySearcher to give me first page, then the next or previous page, it returns me all resulting pages in one bundle.

However, what I need is to explicitely get page after page directly from the AD searcher and to be able to go at least one page forward or backward.

The solution with copying all results to the DataBase and then do the paging is not accepeted by the clent, since it is too inefficient. And since it's a Web app, I cannot keep results in memory either.

I found some hints about COM Interface, but I could not find good and detailed examples or explanations. I aslo found this line of code: DirectoryServices.Interop.IDirectorySearch.ExecuteSearch(), but I don't know which libraries should i add to be able to compile this code.

If somebody could help me out with that problem, any suggestion is welcome, 'cause this issue is eating me alive :)

Thank you!

Error on Display user's fullname using Active Directory in asp.net using vb.net



wi As System.Security.Principal.WindowsIdentity =  _System.Security.Principal.WindowsIdentity.GetCurrent()



Dim a As String() = HttpContext.Current.User.

ASP.NetWindows Application  .NET Framework  C#  VB.Net  ADO.Net  
Sql Server  SharePoint  Silverlight  Others  All   

Hall of Fame    Twitter   Terms of Service    Privacy Policy    Contact Us    Archives   Tell A Friend